Document Number: AUSTIN/23 Title: Projected Joint Revision Project Timeline Revision Date: 1999-03-09 Source: Andrew Josey, Chair Action: for planning Resource Dependencies : Professional Editor (40%) This is an estimated project timeline. This will be updated after each meeting. Known risks: We may decide due to delays in .1a/.2b to push draft 2 and beyond back one quarter which would lead to "technical completion" at the end of the first quarter of Year 2001. This plan allows between 4 and 12 weeks editing cycle for draft production and a 6 week review period for each draft. Milestones: September 1998 - Initial meeting to formulate scope March 1999 - Meeting to produce editing notes for Draft 1. (12 week editing cycle for production of draft 1) June 1st 1999 - Joint Specification Draft 1 available June 1st - July 13th Review Period for Draft 1 July 20-22 Review meeting Montreal Canada (11 week editing cycle for production of draft 2) October 11 1999 - Joint Specification Draft 2 available October 11- Nov 22 Review Period for Draft 2 December 6 - 10 Review meeting (7 week editing cycle for production of draft 3) January 31st 2000 - Joint Specification Draft 3 available Feb 1 - Mar 15 Review period for Draft 3 Mar 27 - 31 Review meeting (6 week editing cycle for production of draft 4) May 15 2000 - Joint Specification Draft 4 available May 15 - July 3 Review period for Draft 4 Jul 10 - 15 Review meeting (7 week editing cycle for production of draft 5) Sep 4 2000 Joint Specification D5 available Sep 4 - Oct 16 Review period for Draft 5 Oct 23-27 Review meeting (4 week editing cycle for sanity draft production) Nov 30 Sanity draft available Dec 1 - Dec 15 Sanity review period Jan 5 - Technical completion