Revision Date: 1999-07-22
Source: Andrew Josey, Chair
Action: for review and planning
This is an estimated project timeline. This will be updated after each meeting.
This document is now superseded by Austin_78.
Changes: July 22 1999 Schedule adjusted .
This plan allows between 4 and 12 weeks editing cycle for draft production and at least 6 week review period for each draft. Note that the exact dates will be adjusted to fit into the week schedules.
Table 1 - Austin Group Specification Draft Schedule
Date | Title of deliverable | Type | Probability | Resources Needed | Assumptions and Dependencies | |
People | Financial | |||||
1 June 1999 | Draft 1 | Draft Standard | 100 | 2 (1 development manager (40%), and one technical editor (40%)) | 10 staff weeks editing + project management .
Signature of MoU between IEEE and The Open Group.
|
|
June 1 - July 14 1999 | Draft 1 Review | Aardvark bug reports | 100 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
Assumes working group review the document. The Open Group and IEEE editors to liaise over style changes.
|
|
20-22 July 1999 | Draft 1 Review Meeting | Change Request Report | 100 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting in Montreal July 20-22
Meeting to be hosted by IEEE PASC, assumes meeting room with external phone line
|
|
October 1999 | Draft 2 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (10 weeks). Project
management (4 days).
External editing costs.
Incorporates style changes and aardvark from D1 review.
that these drafts will slip). No formal review for this document.
|
|
February 2000 | Draft 3 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project management (4 days).
External editing costs for merger of external documents (does not include XRAT)
Merges in the following : Networking interfaces from
XNS 5v2 (includes IPv6) , and IEEE in-flight amendments
|
|
Mar 1 - April 30 2000 | Draft 3 Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
Assumes working group review the document
|
|
May 15-21 2000 | Draft 3 Review Meeting | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting
Meeting to be hosted by TBD, assumes meeting room with external phone line (possibly copenhagen)
|
|
July 2000 | Draft 4 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project Management (4 days).
Completion of document, merges in c9x changes if any. First edition of XRAT . First IEEE ballot.
|
|
Aug 1 - Sep 30 2000 | Draft 4 Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
Assumes working group review the document
|
|
October 10-15 2000 | Draft 4 Review Meeting | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting
Meeting to be hosted by TBD, assumes meeting room with external phone line
|
|
December 2000 | Draft 5 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project management (4 days).
The Open Group Company review draft, and IEEE ballot
|
|
Dec 15 - Feb 14 2001 | Draft 5 Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
Assumes working group review the document
|
|
Mar 1-5 2001 | Draft 5 Review Meeting | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting
Meeting to be hosted by TBD, assumes meeting room with external phone line
|
|
April 5 2001 | Sanity Draft | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (4 weeks).
Project management (4 days)
IEEE Recirculation draft
|
|
April 6 - April 16 2001 | Sanity Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
Assumes working group review the document
|
|
April 23 2001 | Sanity Review Teleconference | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 2 staff days
Teleconference to resolve final issues arising from the Sanity Review
|
|
May 1 2001 | Final Draft | Recirculation Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (1 week per draft)
Enter final approval process. If recirculations are needed they iterate at one month intervals.
|
|