Document Number: AUSTIN/345

Title: Projected Joint Revision Project Timeline

Revision Date: 2007-03-04
Updated after Austin/M13. The most notable change is that the additional standby draft has been dropped from the plan.

Source: Andrew Josey, Chair

Action: for review and planning

This is an estimated project timeline. This will be updated after each meeting.

Note that the exact dates will be adjusted to fit into the week schedules.


Notes on Approval Process

We are aiming for the Sept 2008 Standards Board meeting for IEEE Approval
For IEEE we will need to reform the ballot pool.
We need to start drafting a PAR  for approval within PASC, prior to IEEE.
Suggested to submit a PAR to PASC in June 2006, for two months approval,
Suggest submit PAR to IEEE in August for attention at the Sept 2006 standards board

At ISO the PE will report at the Sept 2006 SC22 what we plan to do. We need to determine
the exact paperwork requirements.
At ISO , the document would progress through the usual 5 stage process
Draft 2 --> CD registration +
   CD Ballot (feature complete)  3 months ballot +  1 month administrative overhead
   FCD Ballot  (doc freezes)   4 months
   FDIS Ballot  (yes/no) 2 months
   Done

We will need to declare a cutoff date for defect report against the existing standard.


Notes on Draft Content and Timeline

Draft 1  :
  Not feature complete
  No new submissions incorporated but all other changes applied from interps, rdvks, sd/5
  Austin Group review only
  Change bars against  existing standard (inc TC1+TC2)
  We could limit this review to the change bar'd text only, with the next draft being open for comments on the whole text?

===> July 31 2006 new material complete


Draft 2
(cannot happen earlier than October 2006) -- actual October 31 2006
    New submissions incorporated
    Feature complete
    We will submit to ISO for concurrent CD registration and CD ballot (3 months)
    Announce to The Open Group membership inviting participation in the Austin Group review
    First IEEE  ballot (3 months)
   Change bars against  existing standard (inc TC1+TC2)
    This will be a 3 month AG review synch'd with the IEEE ballot hopefully also with ISO

===> Ballot resolution meeting (estimated Feb 2007 warm location TBD)

Draft 3
  (cannot happen before April 1 2007) - now scheduled for June 15 2007
    Narrowing down rules apply to Austin Group and IEEE review
    we will make this a 60 day review due to some folks being on vacation.
    Second IEEE ballot (60 day)
    FCD ballot  (4 month)
        (FCD ballot completes no sooner than November 1 2007)
    This will be a 60 day AG review sync'd with IEEE

===> Ballot resolution meeting (face to face Sept 2007 Reading, UK)

Draft 4
   (cannot happen before September  1 2007) -- Scheduled December 15 2007
    The Open Group company review
    IEEE final recirculation ballot
    ISO FDIS ballot (2 months)

Draft 6  Final Publication


Table 1 - Austin Group Specification Draft Schedule

Date Title of deliverable Type Probability Resources Needed Assumptions and Dependencies
People Financial
2006 March 31
1st deadline for announcement of new submissions
Email to Chair
100
 1 (1 development manager) 1 staff day to manage incoming submissions
2006 June 30 
 Draft 1  Draft Standard  80  2 (1 development manager (40%), and one technical editor (40%))   10 staff weeks editing + project management .  Merging of interpretations, and defect report changes identifed in SD/5. The cutoff date for aardvark changes to make this draft is June 12 2006
2006 July 1 - Aug 31
 Draft 1 Review  Aardvark bug reports  80  1 (1 development manager)  3 staff days to manage incoming aardvark and prepare for review meeting.  Assumes working group review the document. 

2006 July 31

Cutoff date for submissions of new material
Text submissions plus editing plan
100
 1 (1 development manager) 1 staff day to manage incoming submissions
Assumes submissions in an acceptable format with clear editing instructions for the merge
2006  Sep 12-15
 Draft 1 Review Meeting  (ISO Editing Group meeting)
 Change Request Report  80  2 (1 development manager, and one technical editor) 6 staff days to attend Review Meeting  This will either  be a meeting in Reading, UK or a series of teleconferences.
IEEE PAR approved 15 Sep 2006.
2006  October 31 
 Draft 2  Draft Standard  80  2 (1 development manager (40%), and one technical editor (40%))  Staff time for production of drafts (10 weeks). Project management (4 days).   Incorporates new submissions, options reorganization, interpretations, SD5 items and aardvark from D1 review. 
2006 Oct 31 - 2007 Jan 31
Draft 2 review
Aardvark bug reports
80
1 (1 development manager)
3 staff days to manage incoming aardvark and prepare for review meeting. This is a 90 day review.First IEEE ballot. Submit to ISO for concurrent CD registration and CD ballot
2007 Feb 26-Mar 2 (week of)
Draft 2 Face to face review meeting
Change Request Report
80
 2 (1 development manager, and one technical editor) 10 staff days plus travel and living costs to attend Review Meeting   Austin Texas. Feb 27-Mar1, assumes meeting room with external phone line, internet link and pc projector. Hosted by IBM
2007  June 15 
 Draft 3
 Draft Standard  80  2 (1 development manager (40%), and one technical editor (40%))  Staff time for production of drafts (6 weeks). Project management (4 days).   Merges in aardvark from D2 review , plus SD5 changes arising from 2004 Edition
2007  June 15 - August 15
 Draft 3 Review  Aardvark bug reports  80  1 (1 development manager)  3 staff days to manage incoming aardvark and prepare for review meeting.  Assumes working group review the document. 2nd IEEE ballot. ISO FCD ballot.
2007  Sep 4
 Draft 3 Review Meeting  Change Request Report  80  2 (1 development manager, and one technical editor)  Face to Face meeting. Reading UK  Meeting to be hosted by The Open Group. Assumes meeting room with external phone line, internet link and pc projector.
2007 Dec 15 
 Draft 4  Draft Standard  80  2 (1 development manager (40%), and one technical editor (40%))  Staff time for production of drafts (6 weeks). Project management (4 days).  The Open Group Company review draft, and IEEE recirculation ballot
2007  Dec 15 -  2008 Jan 31
 Draft 4 Review  Aardvark bug reports  80  1 (1 development manager)  3 staff days to manage incoming aardvark and prepare for review meeting.  Assumes working group review the document
2008  Feb  ??
 Draft 4 Review Meeting
 Change Request Report  80  2 (1 development manager, and one technical editor) TBD   Maybe telco or f2f, TBD.Meeting to be hosted by TBD, assumes meeting room with external phone line, internet link and pc projector.
2008  March 1
 Sanity Draft 5
 Draft Standard  80  2 (1 development manager (40%), and one technical editor (40%))  Staff time for production of drafts (4 weeks). Project management (4 days)
2008  March 1-15
 Sanity Review  Aardvark bug reports  80  1 (1 development manager)  3 staff days to manage incoming aardvark and prepare for review meeting.  Assumes working group review the document
2008  March 22
 Sanity Review telco if needed
 Change Request Report  80  2 (1 development manager, and one technical editor) 2 staff hours    Telco meeting to resolve final issues arising from the Sanity Review
2008  April ??   Final Draft 5.1
 Recirculation Draft Standard  80  2 (1 development manager (40%), and one technical editor (40%))  Staff time for production of drafts (2 week per draft)   Enter final approval process. If recirculations are needed they iterate at one month intervals. Editorial work expected on frontmatter for publication.