Revision Date: 2001-03-17
Source: Andrew Josey, Chair
Action: for review and planning
This is an estimated project timeline. This will be updated after each meeting.
Changes: March 17 2001 Schedule adjusted after March plenary.
Changes: July 22 1999 Schedule adjusted .
Note that the exact dates will be adjusted to fit into the week schedules.
Table 1 - Austin Group Specification Draft Schedule
| Date | Title of deliverable | Type | Probability | Resources Needed | Assumptions and Dependencies | |
| People | Financial | |||||
| 1 June 1999 | Draft 1 | Draft Standard | 100 | 2 (1 development manager (40%), and one technical editor (40%)) | 10 staff weeks editing + project management .
| Signature of MoU between IEEE and The Open Group.
|
|
| June 1 - July 14 1999 | Draft 1 Review | Aardvark bug reports | 100 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
| Assumes working group review the document. The Open Group and IEEE editors to liaise over style changes.
|
|
| 20-22 July 1999 | Draft 1 Review Meeting | Change Request Report | 100 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting in Montreal July 20-22
| Meeting to be hosted by IEEE PASC, assumes meeting room with external phone line
|
|
| October 1999 | Draft 2 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (10 weeks). Project
management (4 days).
External editing costs.
| Incorporates style changes and aardvark from D1 review.
that these drafts will slip). No formal review for this document.
|
|
| February 2000 | Draft 3 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project management (4 days).
External editing costs for merger of external documents (does not include XRAT)
| Merges in the following : Networking interfaces from
XNS 5v2 (includes IPv6) , and IEEE in-flight amendments
|
|
| Mar 1 - April 30 2000 | Draft 3 Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
| Assumes working group review the document
|
|
| May 15-21 2000 | Draft 3 Review Meeting | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting
| Meeting to be hosted by TBD, assumes meeting room with external phone line (possibly copenhagen)
|
|
| July 2000 | Draft 4 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project Management (4 days).
| Completion of document, merges in c9x changes if any. First edition of XRAT . First IEEE ballot.
|
|
| Aug 1 - Sep 30 2000 | Draft 4 Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
| Assumes working group review the document
|
|
| October 10-15 2000 | Draft 4 Review Meeting | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting
| Meeting to be hosted by TBD, assumes meeting room with external phone line
|
|
| December 2000 | Draft 5 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project management (4 days).
| The Open Group Company review draft, and IEEE ballot
|
|
| Dec 15 - Feb 14 2001 | Draft 5 Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
| Assumes working group review the document
|
|
| Mar 5-9 2001 | Draft 5 Review Meeting | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 10 staff days plus travel and living costs to attend Review Meeting
| Meeting to be hosted by TBD, assumes meeting room with external phone line
|
|
| April 20 2001 | Sanity Draft 6 | Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (6 weeks).
Project management (8 days)
| IEEE Recirculation draft
|
|
| April 23 - May 23 2001 | Sanity Review | Aardvark bug reports | 80 | 1 (1 development manager) | 3 staff days to manage incoming aardvark and prepare for
review meeting.
| Assumes working group review the document
|
|
| May 29 - June 1 2001 | Sanity Review Meeting, UK Reading | Change Request Report | 80 | 2 (1 development manager, and one technical editor) | 8 staff days
| Meeting to resolve final issues arising from the Sanity Review
|
|
| June 15 2001 | Final Draft 7 | Recirculation Draft Standard | 80 | 2 (1 development manager (40%), and one technical editor (40%)) | Staff time for production of drafts (2 week per draft)
| Enter final approval process. If recirculations are needed they iterate at one month intervals.
|
|