The COMBINE project is structured in phases and has specific set of milestones. The project is organised as a set of partly overlapping and complementary methodologies and approaches for the building of new components, provision of COTS-components and encapsulation of legacy systems. 

The project is divided into 6 phases summarised as follows:

Main Work Areas

Complete

Phase 0 

Establish baseline and initial requirements

 

March 2001

Phase 1

Develop combined approach for new/COTS components
Demonstration of reference case

 

August 2001

Phase 2

Develop support for reuse/patterns
Demonstration of new/COTS components

 

January 2002

Phase 3

Develop support for evolution/configuration
Demonstration of Reuse

 

June 2002

Phase 4 

Refinement of final deliverables
Demonstration of Evolution/Configuration

 

October 2002

Phase 5

Evaluation and Packaging of results
December 2002

See the Milestones page for the deliverables associated with each project phase.